新闻资讯

UPDATED NEWS

Get You Updated on Playground Equipment News.

How long does it take to build a indoor playground park

Updated:2020-02-21 07:14:51
Views:5737

Now adays the indoor playground parks are very popular,Investing a indoor playground park become one of the low risk investment program .Many investers want to know the how hong does it take to build a indoor playground park?

As a chinese indoor playground supplier who have 9 years indoor playground park building experiance and 5 years running Franchise park experiance.we now answer the questions as follows :

1.Information Collection

Befor building a indoor playground park we need collect a lot of information,like basic project information,park site requirments,franchise qualification .the first period time will depend on your work efficiency,you may meet some problems like the location you found is not fit the reuquirement for open a indoor park or bank not agree this project.As the feedback from our customer,some clients just only need very short time for confirm all this information,some clients even need half year for confirm all the information.

2.Project Planning

when we get all the information for the location where will build this new indoor playground ,we will start to build a cad floor plan provision ,make needed communication, franchise introduction and park market positioning space  and route planning.this progress always cost 3days to one week ,if you have many shareholders for discuss together ,it might be cost more longer time for make the final confirmation with the design .

3.Order confirmation

 After confirm the design,we can start to confirm the equipment order and francnise agreement ,then your company make a payment to the supplier for start production and brand autherization.this progress always spend around 3 or 5 days.

4.Production time 

General Speaking,if you choose a good maunfactory like liben group ,500 square meters park always cost 25 days.if you need the products urgent for the urgent openning time,we can make the time more shorter .if you have 1000 square meters park,the production time will be 35 days,1500 square meters cost 45 days.

5.Shipping time 

The shipping time always depend on which port you need the products shipped to .this time is very easy to know,you can ask your sales consault or check on the internet.if to Mexico it cost 20days for shiping ,7days for clean the custorm.

6.Facility installation

When you get the products,you can start to assemb the equipment,manage the system installation,insepct the park after installation then prepare for openning .if you ask the professional installation team service from supplier,500 square meters always need near 20 days .1000 square meters need 45 days ,1500 square meters need 60 days.






We value your privacy

We use cookies to enhance your browsing experience, serve personalized ads or content, and analyze our traffic. By clicking "Accept All", you consent to our use of cookies.

Consent Preferences

Consent Preferences